The straight story
What's planned, and what the law allows
1953 Republic Ave
- Owner
- Oceanview RE2 LLC (investor group)
- Permit
- PADU-26-0037
- Filed
- March 30, 2026 · in plan review
- Planner
- Justin Arios · 714-754-5667
- Plan
- Demolish the house. Build a 2-story front building split into two 3-BR units with some garage space, plus two detached 2-story 3-BR units behind it with no garage. About 1,200 sq ft each.
- Owner on site
- Not required
900 Arbor St (tract entrance, 19th St side)
- Owner
- Same principal as Republic Ave
- Permit
- To be confirmed with the City
- Filed
- April 17, 2026 · in plan review
- Plan
- Remodel the existing 1,237 sq ft house with a 3-car garage, add a 1,200 sq ft 2nd-floor ADU, a detached 2-story ADU, and an SB 9 unit.
- Parking
- Already limited by red curbs around the property
How four units fit on one lot. California's SB 9 lets an owner build two primary homes on a single-family lot. State ADU law then allows accessory units on top of that. Costa Mesa's code (§13-36) caps the total at four. The state housing department (HCD) has told cities they cannot use SB 9 to block ADUs on a lot that hasn't been split.
Why there's no hearing. Both laws make these permits "ministerial." If the plans meet the City's written, objective standards, the City must approve them, with no public hearing and no notice. Parking, density and lost views can't be grounds for denial.
Step 1 · Sign
Sign to protect Freedom Homes
This petition goes to the Mayor and City Council. Each signature is time-stamped by the server the moment you submit and listed below with your name and street. Your house number and email stay private and go only to the organizers and the City.
Petition text fingerprint (SHA-256): loading…
Public signature roll
Loading signatures…
| # | Name | Street | Relation | Signed (Pacific) | Receipt |
|---|---|---|---|---|---|
| Signatures will appear here as neighbors sign. Be the first. | |||||
How to verify. Every signer gets a receipt: a SHA-256 fingerprint of their public entry and the exact petition text. Paste yours below to confirm your entry is still on the roll and unchanged. Your browser recomputes the fingerprint itself. The roll fingerprint changes whenever any entry is added, changed or removed, so anyone can save it and check later.
Step 2 · Write
Email the City in two minutes
Fill in your details once, then copy each letter or open it in your email app. A sentence in your own words makes a letter count for more. Send each letter yourself. One letter per household member is fine.
Your details
These stay in your browser. Nothing here is sent anywhere until you send the email yourself.
Every avenue
What can actually change the outcome
State law makes an outright stop very unlikely. These are the levers that are real, roughly in order of how soon they matter.
Make the City check every standard
Ministerial doesn't mean automatic. The plans must meet Costa Mesa's written standards, and second-story ADUs have extra conditions. Ask the planner to confirm each one in writing:
- Second-floor ADU portions 25 ft back from the front line, with interior or screened stairs (§13-35(9))
- Side windows within 25 ft of a neighbor's home: 5-ft sill height (§13-35(9))
- No roof decks; balconies only where allowed, screened near neighbors (§13-35(10))
- 6-ft separation between buildings; landscaping and 40% open space (§13-35, §13-32)
- One garage space per primary unit (§13-36(c)(6))
- Demolition limits if the home was tenant-occupied in the last 3 years (§13-36(b))
- The size question: if the City counts the new duplex as multifamily to allow two backyard units, its own multifamily cap (850 sq ft, or 1,000 with 2+ bedrooms) should apply instead of 1,200 (§13-35)
Get the plans: public records request
Request the full plan set, correction letters and correspondence for both properties. A neighbor with design or construction experience can then check them line by line. Template under "Records request" above.
Construction rules and enforcement
Ask for a construction management plan: work hours, contractor parking, staging, dust, street cleanup. Once work starts, report violations to Code Enforcement every time, with photos and times. A documented record matters.
Parking: study, then permit parking
Costa Mesa's residential permit parking program needs a city parking study showing at least 70% occupancy and a petition from 51% of households on a zone of about four blocks. Request a before-and-after study now so the data exists when the units fill up.
Tract deed restrictions (CC&Rs)
Many 1950s–60s tracts recorded "single-family only" covenants. California voids covenants that block ADUs (Civil Code §714.3), but SB 9 itself doesn't address private covenants, so a covenant might still apply to the second primary unit. Pull the tract's recorded restrictions from the OC Clerk-Recorder and have a land-use attorney review them. A few neighbors splitting one consultation is affordable.
Change the rules for the next one
State law bars cities from requiring ADU owners to live on site, so the City can’t sort projects by who owns them. It can set stricter standards for lots with two or more primary homes, the pattern investors use, without touching a homeowner adding one ADU. The owner-occupancy fix itself has to come from Sacramento: SB 9 already requires it for lot splits, but not for two-unit projects like this one. Ask candidates on the Nov 3 ballot where they stand, and write your state Assembly member and Senator.
What tends to backfire
- Arguments about who might rent the units. They carry no weight under state law and can raise fair-housing concerns. Stick to standards, safety, parking and privacy.
- Asking the City to deny a compliant project. State law bars it, and the state can penalize cities that do. Ask for strict compliance instead.
- Confronting the owner, contractors or future tenants. Keep everything in writing, factual and with the City.